We had the contractors booked in since early December, and with a stroke of luck, received our building permit the day before digging commenced.
Because we needed to insert a drain on the inside the footing around the sunken lounge, and we have curved steps leading into the lounge, we were left with this mini Grand Canyon.
Fortunately we didn’t come across too many large rocks, and the boxing kicked off on the second day. The contractors were somewhat dismayed by the amount of boxing that was required to reach the various levels, and our house soon became known as “Box City”.
The curved wall and steps was quite a challenge for them, and they did question whether we knew they were concreters not carpenters.
If the amount of boxing and the curves wasn’t enough to frustrate them, Karim following them around with his right royal pain in the arse prism to ensure they were within millimetric accuracy certainly did, especially when they were expected to maintain that accuracy while bashing star pickets into hard, rocky ground!
That said, the contractors did love having the total station on site, especially the plumber and electrician so we could make sure the shower actually did end up over the waste pipe, and the gas was where the stove will be.
And eventually they got revenge by asking Karim to get any loose material out of all the pier holes ha ha
We had always tried to keep the plumbing central in the design of the home, and were pleased to see that the entire job only used three lengths of pipe.
Jack and I placed a timber rebate along the straw bale curved wall, which will act as a render stop…
And made some formwork for the decking piers with off-cuts from industrial plumbing suppliers.
Having set those at the right level, it was really easy to bring the concrete to the right level. Though it was an opportunity for the contractors to take revenge by constantly checking my work and telling me that I was 5mm too high!
By the third day all the lovely chalk lines were gone and the nice level site became quite a mess
Much to the dismay of the project manager…
But once the sand and gravel went down, the site started to look more ordered.
The site wasn't quite ready for the pour in time, which was happening first thing Monday morning, so we were taught how to lay all the insulation, moister barriers and slab mesh so we could finish the job ourselves over the weekend. It was nice to be able to do so much ourselves, and of course we saved quite a bit of money in labour.
After a manic weekend, Karim left for Manilla at 3.30am, so he missed the pour, however we were ready for the concrete trucks.
It was a hectic day, but by the end, we not only had fabulous foundations, the contractor charged us less than his quote even though it took longer than expected... a good deed you may no longer find in too many places other than Tassie Mania.
Carly helped put the left over concrete in the bottom of a new storm water drain. But more importantly, while all this was going on, she took on the role of master chef, harvesting food from the garden and preparing delicious, healthy meals to sustain us throughout the challenge.
And John watered the foundations every hour that evening and the next day because the weather was quite warm and we needed to avoid the concrete setting too quickly.
Ben and John then spent the next few days cleaning the site (which looked like a bomb had hit it), ready for the build to commence. We realised that the contractors had left their whacker packer behind, so rushed in a delivery of gravel to lay in the earthen floor areas and used the machine to compact it, which gives us a clean, hard surface to work on in those areas.
We also placed temporary drains through the footings (bottom centre), so that any rain can exit the building until the roof is constructed. This photo also shows what a wonderful job the contractors did of the foundation for the curved wall, let alone the whole project, as they reached accuracy of within three millimetres. We placed recycled plastic containers over any protruding steel bars (which will reinforce blockwork), to ensure no-one gets staked on them if they trip.
So now the build is in full swing, and to give you a sneak preview, the first four columns have been raised!
Who knows what stage we’ll be at by our end of February update, but just to put it out there… it would be truly wonderful if the curved clerestory wall is in the air.